Case studies

Power Pole Jobs We've Completed Across Sydney

Real jobs from the High Demand Power Poles team: what we were called out for, what we did and how it finished.

Emergency Pole Replacement After a Vehicle Impact in Enfield
Enfield

Emergency Pole Replacement After a Vehicle Impact in Enfield

A vehicle struck the private power pole at an Enfield property and the supply needed to be made safe and restored urgently.

Emergency Pole Replacement After a Vehicle Impact in Enfield
Enfield

Emergency Pole Replacement After a Vehicle Impact in Enfield

Why we were called

A vehicle struck the private power pole at an Enfield property and the supply needed to be made safe and restored urgently.

What we did
  • Supplied a generator to keep the property powered
  • Removed the damaged pole and footing
  • Installed a new pole
  • Ran a three-phase overhead service to the Ausgrid asset pole
  • Tested and commissioned the new supply
Result

The damaged pole was replaced with a new pole and a three-phase overhead service, tested and commissioned.

Termite-Damaged Timber Pole Replaced With Galvanised Steel in Dulwich Hill
Dulwich Hill

Termite-Damaged Timber Pole Replaced With Galvanised Steel in Dulwich Hill

The existing timber pole at a Dulwich Hill property had been damaged by termites and was no longer safe to carry the service.

Termite-Damaged Timber Pole Replaced With Galvanised Steel in Dulwich Hill
Dulwich Hill

Termite-Damaged Timber Pole Replaced With Galvanised Steel in Dulwich Hill

Why we were called

The existing timber pole at a Dulwich Hill property had been damaged by termites and was no longer safe to carry the service.

What we did
  • Installed a new 6.5m galvanised steel pole
  • Installed 16mm XLPE underground consumer mains
  • Tested the installation before energisation
Result

The property now has a galvanised steel pole that will not rot or attract termites.

Permanent Poles for a Two Dwelling Site in North Nowra
North Nowra

Permanent Poles for a Two Dwelling Site in North Nowra

A North Nowra site with two dwellings needed its temporary builders supply pole replaced with a full-length pole, plus a second private pole for the second dwelling.

Permanent Poles for a Two Dwelling Site in North Nowra
North Nowra

Permanent Poles for a Two Dwelling Site in North Nowra

Why we were called

A North Nowra site with two dwellings needed its temporary builders supply pole replaced with a full-length pole, plus a second private pole for the second dwelling.

What we did
  • Removed the temporary builders supply pole and installed a full-length pole in the same spot
  • Installed a second private pole for the second dwelling
  • Brought the service mains up both poles and ran a new overhead to the second pole
  • Moved the smart meter from the builders supply board to the new switchboard on unit 1
  • Sealed and made ready both units' switchboards
Result

Both dwellings now have permanent private poles and switchboards ready for service, with the site off its temporary builders supply.

Temporary Builders Supply Pole for a Duplex in West Ryde
West Ryde

Temporary Builders Supply Pole for a Duplex in West Ryde

A West Ryde duplex site needed its existing supply disconnected and temporary builders power set up on a private pole that will later become permanent.

Temporary Builders Supply Pole for a Duplex in West Ryde
West Ryde

Temporary Builders Supply Pole for a Duplex in West Ryde

Why we were called

A West Ryde duplex site needed its existing supply disconnected and temporary builders power set up on a private pole that will later become permanent.

What we did
  • Disconnected the existing supply
  • Installed a private pole on site
  • Set up a temporary builders supply on the pole
  • Installed 4G site cameras
Result

The site has construction power from the start, on a pole positioned to become the permanent supply for the duplex later.

Second Private Pole for a Duplex in Georges Hall
Georges Hall

Second Private Pole for a Duplex in Georges Hall

A Georges Hall duplex already had a private pole on one side and needed a second for the other dwelling.

Second Private Pole for a Duplex in Georges Hall
Georges Hall

Second Private Pole for a Duplex in Georges Hall

Why we were called

A Georges Hall duplex already had a private pole on one side and needed a second for the other dwelling.

What we did
  • Installed a private pole for the second side of the duplex
  • Ran a new overhead to the pole
  • Relocated the meter from the temporary board to the permanent board
  • Completed the connection
Result

Both sides of the duplex now have their own private pole, with the second side moved off temporary supply onto its permanent board.

Two New Poles Installed in Wentworthville
Wentworthville

Two New Poles Installed in Wentworthville

A Wentworthville site needed two new poles set in place for its supply.

Two New Poles Installed in Wentworthville
Wentworthville

Two New Poles Installed in Wentworthville

Why we were called

A Wentworthville site needed two new poles set in place for its supply.

What we did
  • Supplied and delivered two new poles to site
  • Set both poles in concrete
  • Fitted a J hook to each pole
  • Fitted a cap to each pole
Result

Both poles are set in concrete with hooks and caps fitted, ready for their overhead connections.

Private Pole and Three Phase Upgrade in Leichhardt
Leichhardt

Private Pole and Three Phase Upgrade in Leichhardt

A Leichhardt property was moving to a three-phase supply with a new private pole and a pole-mounted main switchboard.

Private Pole and Three Phase Upgrade in Leichhardt
Leichhardt

Private Pole and Three Phase Upgrade in Leichhardt

Why we were called

A Leichhardt property was moving to a three-phase supply with a new private pole and a pole-mounted main switchboard.

What we did
  • Installed a new private power pole with earthing at the pole
  • Ran new three-phase overhead service mains and overhead consumer mains
  • Installed a new point of attachment hook centred on the roof
  • Mounted a 600x600 switchboard on the pole with three service fuses, a neutral link, a three-phase main switch and a circuit breaker
  • Ran three-phase consumer mains down the pole to the switchboard and connected them at the new point of attachment
Result

The property is now on a three-phase supply through its own private pole, with a new pole-mounted main switchboard and earthing in place.

Temporary Builders Supply and Private Pole in Rose Bay
Rose Bay

Temporary Builders Supply and Private Pole in Rose Bay

A Rose Bay building site needed its existing supply disconnected and a temporary builders supply set up on a private pole for construction.

Temporary Builders Supply and Private Pole in Rose Bay
Rose Bay

Temporary Builders Supply and Private Pole in Rose Bay

Why we were called

A Rose Bay building site needed its existing supply disconnected and a temporary builders supply set up on a private pole for construction.

What we did
  • Disconnected the existing supply
  • Installed a new private pole
  • Installed a temporary builders supply on the pole
  • Installed a construction site camera
Result

The site now has temporary construction power on its own private pole, with a site camera in place.

Pole Replacement for Three Phase Supply in Earlwood
Earlwood

Pole Replacement for Three Phase Supply in Earlwood

An Earlwood property's existing pole needed replacing as part of a move to three-phase supply, with family members at home throughout the works.

Pole Replacement for Three Phase Supply in Earlwood
Earlwood

Pole Replacement for Three Phase Supply in Earlwood

Why we were called

An Earlwood property's existing pole needed replacing as part of a move to three-phase supply, with family members at home throughout the works.

What we did
  • Disconnected the mains at the point of attachment
  • Removed the existing pole
  • Installed a new 7.2m pole for the three-phase supply
  • Supplied a complimentary generator to keep the household powered during the works
Result

The property now has a new 7.2m pole ready for its three-phase supply, and the household kept power to its appliances throughout the works.

Private Pole Install and Overhead Connection in North St Marys
North St Marys

Private Pole Install and Overhead Connection in North St Marys

A North St Marys property needed a private pole installed and connected to the overhead supply, ready for three-phase metering.

Private Pole Install and Overhead Connection in North St Marys
North St Marys

Private Pole Install and Overhead Connection in North St Marys

Why we were called

A North St Marys property needed a private pole installed and connected to the overhead supply, ready for three-phase metering.

What we did
  • Installed a new private pole
  • Made the overhead connection to the pole
  • Fitted the three-phase meter sticker and tagged the installation
  • Lodged the meter application
Result

The private pole is installed and connected, with the site tagged and the three-phase meter application lodged.

Private Pole and Three Phase Switchboard in North Sydney
North Sydney

Private Pole and Three Phase Switchboard in North Sydney

A North Sydney property needed a new private pole and a new three-phase main switchboard.

Private Pole and Three Phase Switchboard in North Sydney
North Sydney

Private Pole and Three Phase Switchboard in North Sydney

Why we were called

A North Sydney property needed a new private pole and a new three-phase main switchboard.

What we did
  • Dug the footing and concreted in a new private pole
  • Installed a new 600x600 three-phase switchboard with a pre-made panel
  • Fitted three-phase surge protection and a new earth stake
  • Installed a fascia bracket and ran the overhead cable and 16mm XLPE mains
Result

The property now has its own private pole and a new three-phase switchboard with surge protection and earthing in place.

Private Pole Install and Permanent Connection in Georges Hall
Georges Hall

Private Pole Install and Permanent Connection in Georges Hall

A Georges Hall property needed a new private pole and a permanent single-phase connection, with provision left for an underground supply later.

Private Pole Install and Permanent Connection in Georges Hall
Georges Hall

Private Pole Install and Permanent Connection in Georges Hall

Why we were called

A Georges Hall property needed a new private pole and a permanent single-phase connection, with provision left for an underground supply later.

What we did
  • Installed a new private pole
  • Left provision in the pole for a future underground supply
  • Ran new single-phase overhead service mains to the pole
  • Completed the metering and permanent connection
Result

The property now has a permanent single-phase supply on its own private pole, with provision in place for an underground connection later.

New Private Pole and Overhead Service in Killara
Killara

New Private Pole and Overhead Service in Killara

A Killara property needed a new private pole with a single-phase overhead service from the network pole.

New Private Pole and Overhead Service in Killara
Killara

New Private Pole and Overhead Service in Killara

Why we were called

A Killara property needed a new private pole with a single-phase overhead service from the network pole.

What we did
  • Installed a new private pole
  • Supplied and installed a private pillar
  • Ran single-phase overhead service mains from the network pole to the private pole
  • Fitted fuses to protect the existing underground consumer mains
Result

The property is now fed from the network through its own private pole, and the existing underground consumer mains are protected by new fuses.

Ready to secure your property with Power Poles service?

Fill out the form and our expert team will get back to you shortly. Whether it’s an emergency or a planned installation, we’re ready to help—fast, safe, and professional.