Case studies

Power Pole Jobs We've Completed Across Sydney

Real jobs from the High Demand Power Poles team: what we were called out for, what we did and how it finished.

Emergency Pole Replacement After Storm Collapse, Seaforth
Seaforth

Emergency Pole Replacement After Storm Collapse, Seaforth

A private power pole collapsed in a storm at this Seaforth property and Ausgrid disconnected the supply for safety. A Level 2 ASP was urgently needed to replace the pole and restore the overhead supply.

View case study →
Emergency Pole Replacement After Storm Collapse, Seaforth
Seaforth

Emergency Pole Replacement After Storm Collapse, Seaforth

Why we were called

A private power pole collapsed in a storm at this Seaforth property and Ausgrid disconnected the supply for safety. A Level 2 ASP was urgently needed to replace the pole and restore the overhead supply.

What we did
  • Attended site for an emergency assessment and make safe.
  • Isolated the damaged supply and confirmed the network disconnection.
  • Removed the failed private pole and unsafe components.
  • Installed a new private pole on a compliant concrete footing.
  • Reinstalled the overhead service mains to the new pole and reconnected the consumer mains to the switchboard.
  • Tested, tagged and commissioned the installation.
Result

The property has a compliant replacement private pole with its overhead service mains reconnected and power fully restored after the storm.

Rusted Steel Private Pole Replacement, Middle Cove
Middle Cove

Rusted Steel Private Pole Replacement, Middle Cove

The owner of this Middle Cove home received an Ausgrid defect notice for a private steel pole that had rusted badly at the base. Only a licensed Level 2 ASP can disconnect, remove and replace a live pole like this. The old pole also sat close to the water mains, so the new one had to be repositioned.

View case study →
Rusted Steel Private Pole Replacement, Middle Cove
Middle Cove

Rusted Steel Private Pole Replacement, Middle Cove

Why we were called

The owner of this Middle Cove home received an Ausgrid defect notice for a private steel pole that had rusted badly at the base. Only a licensed Level 2 ASP can disconnect, remove and replace a live pole like this. The old pole also sat close to the water mains, so the new one had to be repositioned.

What we did
  • Safely disconnected and coiled the overhead consumer mains at the Ausgrid pole.
  • Extracted the rusted steel pole and cut it off below ground level.
  • Cored a new 1m hole slightly forward of the original position to clear the water mains, and installed the new pole.
  • Ran and sleeved new consumer mains up the pole, fitted new connectors and restrung the overheads.
  • Tested and tagged the installation.
Result

The Ausgrid defect was rectified and the safety risk from the corroded pole removed. Power was restored and the installation passed all testing.

Timber Private Pole Replacement, Menangle Park
Menangle Park

Timber Private Pole Replacement, Menangle Park

A deteriorated timber private pole at this Menangle Park property had reached the end of its service life and was a safety risk. Because the pole carries the point of attachment, only a Level 2 ASP can lawfully disconnect and reconnect the network supply.

View case study →
Timber Private Pole Replacement, Menangle Park
Menangle Park

Timber Private Pole Replacement, Menangle Park

Why we were called

A deteriorated timber private pole at this Menangle Park property had reached the end of its service life and was a safety risk. Because the pole carries the point of attachment, only a Level 2 ASP can lawfully disconnect and reconnect the network supply.

What we did
  • Isolated and disconnected the service, then removed the failing timber pole.
  • Supplied and installed a new 9.2m 4kN rated timber pole to Endeavour Energy network standards.
  • Drove a new earth stake to AS/NZS 3000:2018 requirements.
  • Lodged the Notice of Service Work with Endeavour Energy on completion.
  • Reconnected supply once the pole replacement was certified.
Result

The site now has a structurally sound, compliant private pole with certified earthing and a secure point of attachment.

Timber Private Pole Replacement and Overhead Mains, Yerrinbool
Yerrinbool

Timber Private Pole Replacement and Overhead Mains, Yerrinbool

An ageing private pole supporting several supplies at this Yerrinbool site had become unstable. It needed to be replaced and the overhead service restored safely, with the work done on a weekend to limit disruption.

View case study →
Timber Private Pole Replacement and Overhead Mains, Yerrinbool
Yerrinbool

Timber Private Pole Replacement and Overhead Mains, Yerrinbool

Why we were called

An ageing private pole supporting several supplies at this Yerrinbool site had become unstable. It needed to be replaced and the overhead service restored safely, with the work done on a weekend to limit disruption.

What we did
  • Excavated the old footing and removed and disposed of the existing timber pole.
  • Installed a new 9.5m timber private pole, then backfilled and compacted it for stability.
  • Reconnected all the switchboards supplied from the pole, with isolation, termination, testing and reinstatement of supply.
  • Installed new overhead consumer mains with the required clearances.
  • Retensioned the existing overhead signals cable across three poles and fitted a new bracket where one had slipped.
  • Worked from an elevated work platform for safe access.
Result

The site now has a stable, compliant private pole supporting its multiple supplies, with overhead cables correctly tensioned and supported.

Emergency Pole Replacement After Lightning Strike, Cronulla
Cronulla

Emergency Pole Replacement After Lightning Strike, Cronulla

During a severe storm, lightning struck a private power pole in Cronulla and brought the pole and switchboard down, leaving live conductors exposed. A Level 2 ASP was urgently needed to make the site safe, replace the damaged infrastructure and restore supply.

View case study →
Emergency Pole Replacement After Lightning Strike, Cronulla
Cronulla

Emergency Pole Replacement After Lightning Strike, Cronulla

Why we were called

During a severe storm, lightning struck a private power pole in Cronulla and brought the pole and switchboard down, leaving live conductors exposed. A Level 2 ASP was urgently needed to make the site safe, replace the damaged infrastructure and restore supply.

What we did
  • Attended the emergency make safe after the lightning strike.
  • Removed the fallen private pole and the damaged switchboard.
  • Core drilled a new footing and installed a replacement private power pole.
  • Installed a new 600x600 switchboard and rebuilt the internal components, with new three phase consumer mains and protected submains conduit.
  • Installed an earth stake, service fuses and protection devices, tested the existing overhead service cable and reconnected it to the new pole.
  • Tested, energised and commissioned the installation.
Result

The property was made safe and restored with a new compliant private pole and a rebuilt switchboard supporting a three phase supply.

Private Power Pole and Consumer Mains Upgrade, Gymea Bay
Gymea Bay

Private Power Pole and Consumer Mains Upgrade, Gymea Bay

A failed point of attachment bracket at this Gymea Bay home left overhead conductors exposed, a serious safety risk. The private pole and consumer mains no longer met current standards, and a Level 2 ASP was needed to isolate the overhead service before work could start.

View case study →
Private Power Pole and Consumer Mains Upgrade, Gymea Bay
Gymea Bay

Private Power Pole and Consumer Mains Upgrade, Gymea Bay

Why we were called

A failed point of attachment bracket at this Gymea Bay home left overhead conductors exposed, a serious safety risk. The private pole and consumer mains no longer met current standards, and a Level 2 ASP was needed to isolate the overhead service before work could start.

What we did
  • Isolated and disconnected the failed point of attachment bracket and overhead conductors under Level 2 ASP authority.
  • Supplied and installed a new 6.5m galvanised steel private pole, set to achieve 3.0m clearance over the pergola.
  • Fitted a new point of attachment bracket with a 900mm standoff arm and new 16mm2 consumer mains.
  • Installed an 80A HRC service protection device and coordinated reconnection with Ausgrid.
  • Lodged the Notice of Service Work and Certificate of Compliance for Electrical Work.
Result

The property now has a compliant private pole and consumer mains installation, with supply safely restored and all compliance documentation lodged.

Fallen Pole Replacement and Switchboard Upgrade, Bilgola Plateau
Bilgola Plateau

Fallen Pole Replacement and Switchboard Upgrade, Bilgola Plateau

A private power pole had fallen at this Bilgola Plateau property, leaving the premises without a safe and stable electrical supply. The pole needed urgent replacement, along with an upgrade of the electrical setup to get power back on.

View case study →
Fallen Pole Replacement and Switchboard Upgrade, Bilgola Plateau
Bilgola Plateau

Fallen Pole Replacement and Switchboard Upgrade, Bilgola Plateau

Why we were called

A private power pole had fallen at this Bilgola Plateau property, leaving the premises without a safe and stable electrical supply. The pole needed urgent replacement, along with an upgrade of the electrical setup to get power back on.

What we did
  • Cleared roots and ground obstructions, then removed the damaged pole and disconnected the overhead service.
  • Installed a new private power pole on a concrete footing.
  • Reinstalled and secured the overhead service mains and connected the consumer mains.
  • Fitted a new 600x600 switchboard on the pole and upgraded the sub board with RCBO protection and a three phase main switch.
  • Installed a new earth stake, service fuses and a smart meter, then tested and commissioned the installation.
Result

The property has a restored, compliant supply on a new private pole with an upgraded switchboard and modern protection.

Private Power Pole Replacement, Picnic Point
Picnic Point

Private Power Pole Replacement, Picnic Point

The existing steel service pole at this Picnic Point property had deteriorated badly and was a safety risk, with the power supply to the home at risk of failing. Because the overhead consumer mains had to be disconnected and reconnected, the job needed a licensed Level 2 ASP electrician.

View case study →
Private Power Pole Replacement, Picnic Point
Picnic Point

Private Power Pole Replacement, Picnic Point

Why we were called

The existing steel service pole at this Picnic Point property had deteriorated badly and was a safety risk, with the power supply to the home at risk of failing. Because the overhead consumer mains had to be disconnected and reconnected, the job needed a licensed Level 2 ASP electrician.

What we did
  • Removed and safely disposed of the defective steel service pole.
  • Supplied and installed a new 6.5m galvanised private service pole on a new concrete footing.
  • Transferred and reconnected the existing single phase overhead consumer mains and associated equipment.
  • Installed all required brackets and fittings, then tested and commissioned the installation.
  • Notified the electricity distributor and issued a Certificate of Compliance for Electrical Work.
Result

The property now has a safe, compliant private pole with its overhead supply reconnected. All compliance paperwork was completed on the day of the works.

Fallen Pole Replacement and Three Phase Service Restoration, Padstow
Padstow

Fallen Pole Replacement and Three Phase Service Restoration, Padstow

A fallen power pole at a multi-dwelling property in Padstow left six townhouses without power and created an urgent safety hazard. The three phase supply had to be fully restored and commissioned before residents could return to the site.

View case study →
Fallen Pole Replacement and Three Phase Service Restoration, Padstow
Padstow

Fallen Pole Replacement and Three Phase Service Restoration, Padstow

Why we were called

A fallen power pole at a multi-dwelling property in Padstow left six townhouses without power and created an urgent safety hazard. The three phase supply had to be fully restored and commissioned before residents could return to the site.

What we did
  • Safely removed the fallen pole and all associated overhead conductors from site.
  • Core drilled and installed a new 6.5m timber power pole, set and plumbed to Endeavour Energy standards.
  • Cut and prepared the new pole for the three phase service cable entry point.
  • Performed insulation resistance testing, reconnected at the new point of attachment and commissioned all six dwellings.
Result

All six Padstow townhouses had power safely restored after full testing and commissioning of the new three phase service. Works were completed to Endeavour Energy network standards, with supply confirmed at every dwelling before sign-off.

Private Pole and Three Phase Supply in Eastwood
Eastwood

Private Pole and Three Phase Supply in Eastwood

A new duplex development in Eastwood needed permanent three phase supply, with underground consumer mains to each meter panel. Installing private poles, overhead service mains and network connections is Level 2 ASP work.

View case study →
Private Pole and Three Phase Supply in Eastwood
Eastwood

Private Pole and Three Phase Supply in Eastwood

Why we were called

A new duplex development in Eastwood needed permanent three phase supply, with underground consumer mains to each meter panel. Installing private poles, overhead service mains and network connections is Level 2 ASP work.

What we did
  • Installed a new private power pole and ran three phase overhead service mains across the road from the network
  • Dug trenches to about 500mm through rubble, rock, reo, clay and tree roots, and exposed the existing conduits
  • Routed the underground consumer mains through tight conduit sections and terminated them at the pole and switchboard
  • Installed NBN conduit to the boundary and underground cable protection, then backfilled and reinstated the trenches
  • Connected, tested, sealed and labelled both boards and documented the service routes
Result

Both boards at the Eastwood development are connected, tested and sealed, and the site was left clean. The NBN conduit is in place for the telco to finish the lead-in.

Private Pole for a Knockdown Rebuild in Ryde
Ryde

Private Pole for a Knockdown Rebuild in Ryde

An existing house in Ryde was about to be demolished, and the aerials had to come off it first. The supply needed moving to a new private pole for the builder. Overhead service work is Level 2 ASP work.

View case study →
Private Pole for a Knockdown Rebuild in Ryde
Ryde

Private Pole for a Knockdown Rebuild in Ryde

Why we were called

An existing house in Ryde was about to be demolished, and the aerials had to come off it first. The supply needed moving to a new private pole for the builder. Overhead service work is Level 2 ASP work.

What we did
  • Disconnected the overhead service mains from the house due for demolition
  • Reconnected the overhead service mains to a new private power pole as a permanent solution
  • Disconnected and reconnected the metering equipment and processed the metering paperwork
  • Energised, tested and commissioned the new setup
Result

The supply now runs from a new private pole, so the demolition can go ahead. The setup was tested and is fully operational.

Core Drilled Pole and Builders Supply in Malabar
Malabar

Core Drilled Pole and Builders Supply in Malabar

A Malabar home was due to be demolished, and the builder needed the power disconnected and a temporary builders supply. The pole had to sit behind a wall, with the overheads coming from the street pole nearest the water so they would not cross the front of the house. This is Level 2 ASP work.

View case study →
Core Drilled Pole and Builders Supply in Malabar
Malabar

Core Drilled Pole and Builders Supply in Malabar

Why we were called

A Malabar home was due to be demolished, and the builder needed the power disconnected and a temporary builders supply. The pole had to sit behind a wall, with the overheads coming from the street pole nearest the water so they would not cross the front of the house. This is Level 2 ASP work.

What we did
  • Disconnected the existing supply ahead of the demolition
  • Core drilled and installed a new private pole behind the wall
  • Ran the overheads from the other street pole so they stay clear of the front of the house
  • Installed the temporary builders supply on the new pole
Result

The site is ready for demolition with a temporary builders supply on a new pole. The overheads stay clear of the front of the house.

New Pole and Three Phase Upgrade in Vaucluse
Vaucluse

New Pole and Three Phase Upgrade in Vaucluse

The owners of a Vaucluse property wanted the point of attachment moved about 3 metres further back and the supply upgraded to three phase. That meant a new private pole, new overhead service mains and network connection work, all Level 2 ASP work.

View case study →
New Pole and Three Phase Upgrade in Vaucluse
Vaucluse

New Pole and Three Phase Upgrade in Vaucluse

Why we were called

The owners of a Vaucluse property wanted the point of attachment moved about 3 metres further back and the supply upgraded to three phase. That meant a new private pole, new overhead service mains and network connection work, all Level 2 ASP work.

What we did
  • Core drilled through sandstone and installed a new 6.5m galvanised steel private pole
  • Installed new three phase overhead service mains from the Ausgrid pole to the new private pole
  • Replaced the old 16mm² wiring with 25mm² XLPE consumer mains, a 100A three phase main switch, circuit breaker and service fuses
  • Relocated the temporary builders supply, installed an earth stake and removed the old timber pole
  • Restored supply and completed testing, commissioning, sealing and compliance paperwork
Result

The Vaucluse property now runs on a three phase supply from a new galvanised pole. The old timber pole is gone and the installation is fully commissioned.

Builders Supply to Permanent Board in Loftus
Loftus

Builders Supply to Permanent Board in Loftus

Construction at a Loftus home had reached the point where the temporary builders supply could come off and the meter could move to the new board. Disconnection and reconnection work at the pole is Level 2 ASP work.

View case study →
Builders Supply to Permanent Board in Loftus
Loftus

Builders Supply to Permanent Board in Loftus

Why we were called

Construction at a Loftus home had reached the point where the temporary builders supply could come off and the meter could move to the new board. Disconnection and reconnection work at the pole is Level 2 ASP work.

What we did
  • Disconnected the temporary builders supply and removed the meter from the temporary board
  • Installed a new board, then relocated and wired the single phase meter
  • Reconnected the consumer mains for the new switchboard at the private pole
  • Tested and secured the board, finishing in about an hour on site
Result

The Loftus home is now running from its permanent board with the meter in its new position. Nothing was removed from the pole.

Private Pole Mains Connection in Sylvania
Sylvania

Private Pole Mains Connection in Sylvania

A builder in Sylvania needed the consumer mains from a new home connected at the top of its private pole to the aerial. Connections at the pole are Level 2 ASP work.

View case study →
Private Pole Mains Connection in Sylvania
Sylvania

Private Pole Mains Connection in Sylvania

Why we were called

A builder in Sylvania needed the consumer mains from a new home connected at the top of its private pole to the aerial. Connections at the pole are Level 2 ASP work.

What we did
  • Fed the consumer mains up through the private pole and completed the anaconda work
  • Stripped and cut the consumer mains to length at the top of the pole
  • Connected the consumer mains to the overheads with double and single bolt HSCs
  • Removed the fuse and neutral at the switchboard while the connections were made
  • Tested for voltage and completed an NST test, with all results positive
Result

The consumer mains are now connected to the overheads at the private pole. All tests came back positive.

New Pole and Builders Supply in Ryde
Ryde

New Pole and Builders Supply in Ryde

A building site in Ryde needed a temporary builders supply on a new pole, with the existing overhead lines moved across to it. Pole and overhead work is Level 2 ASP work.

View case study →
New Pole and Builders Supply in Ryde
Ryde

New Pole and Builders Supply in Ryde

Why we were called

A building site in Ryde needed a temporary builders supply on a new pole, with the existing overhead lines moved across to it. Pole and overhead work is Level 2 ASP work.

What we did
  • Installed a new pole with a hook and cap
  • Set up the TBS and ran consumer mains in 16m of 6mm STI and 7m of 25mm rubber hose
  • Installed an earth stake set in 2 bags of concrete, with earth cable, clamp and tag
  • Relocated the existing overhead lines to the new pole using 2 and 4 bolt HSCs
Result

The site has a temporary builders supply on its own pole, earthed and ready for construction.

Builders Supply Removal and Meter Relocation in Sans Souci
Sans Souci

Builders Supply Removal and Meter Relocation in Sans Souci

A Sans Souci build was ready to come off temporary power. The meter needed relocating and the supply connecting onto new service mains already in position. Disconnection and reconnection work is Level 2 ASP work.

View case study →
Builders Supply Removal and Meter Relocation in Sans Souci
Sans Souci

Builders Supply Removal and Meter Relocation in Sans Souci

Why we were called

A Sans Souci build was ready to come off temporary power. The meter needed relocating and the supply connecting onto new service mains already in position. Disconnection and reconnection work is Level 2 ASP work.

What we did
  • Disconnected the temporary builders supply
  • Relocated the existing meter to the prepared switchboard
  • Connected the supply onto the new service mains already in position
  • Reconnected power to the property
Result

The property now runs on its permanent supply. The temporary builders supply is gone and the meter is in its final position.

Duplex Private Pole and Three Phase Upgrade in Old Erowal Bay
Old Erowal Bay

Duplex Private Pole and Three Phase Upgrade in Old Erowal Bay

A site in Old Erowal Bay was running on a single phase temporary pole, but the build had become a duplex. Both sides needed three phase from the street and the new side needed connecting. Pole installs, supply upgrades and new connections are Level 2 ASP work.

View case study →
Duplex Private Pole and Three Phase Upgrade in Old Erowal Bay
Old Erowal Bay

Duplex Private Pole and Three Phase Upgrade in Old Erowal Bay

Why we were called

A site in Old Erowal Bay was running on a single phase temporary pole, but the build had become a duplex. Both sides needed three phase from the street and the new side needed connecting. Pole installs, supply upgrades and new connections are Level 2 ASP work.

What we did
  • Installed a new private pole for the duplex
  • Upgraded both sides from single phase to three phase from the street
  • Installed two new three phase meters
  • Connected and livened up the new side of the duplex
Result

Both dwellings now run on three phase supply from a private pole. The new side is livened and ready to use.

Private Pole and Temporary Board Install in Lilli Pilli
Lilli Pilli

Private Pole and Temporary Board Install in Lilli Pilli

The owners of a Lilli Pilli property did not want their overhead service crossing the driveway, and the site needed construction power for upcoming building works. Moving a point of attachment and running new service mains from the Ausgrid pole is Level 2 ASP work.

View case study →
Private Pole and Temporary Board Install in Lilli Pilli
Lilli Pilli

Private Pole and Temporary Board Install in Lilli Pilli

Why we were called

The owners of a Lilli Pilli property did not want their overhead service crossing the driveway, and the site needed construction power for upcoming building works. Moving a point of attachment and running new service mains from the Ausgrid pole is Level 2 ASP work.

What we did
  • Disconnected the existing point of attachment and service mains from the Ausgrid network pole
  • Supplied and installed a new single phase private service pole
  • Ran new overhead service mains from the Ausgrid pole to the private pole
  • Fitted a temporary main switchboard to the pole for the construction works
  • Completed testing plus the Ausgrid NOSW and CCEW paperwork
Result

The overhead service now runs to a private pole clear of the driveway. The builders have temporary power on site for the works.

Emergency Pole Replacement After a Sunday Outage in Blacktown
Blacktown

Emergency Pole Replacement After a Sunday Outage in Blacktown

A Blacktown home lost power on a Sunday after Endeavour Energy cut the supply over unsafe consumer mains and arcing at the point of attachment. The timber pole was also termite damaged and unstable. Pole replacement and network connections are Level 2 ASP work.

View case study →
Emergency Pole Replacement After a Sunday Outage in Blacktown
Blacktown

Emergency Pole Replacement After a Sunday Outage in Blacktown

Why we were called

A Blacktown home lost power on a Sunday after Endeavour Energy cut the supply over unsafe consumer mains and arcing at the point of attachment. The timber pole was also termite damaged and unstable. Pole replacement and network connections are Level 2 ASP work.

What we did
  • Investigated the outage and made the site safe so power was restored the same day
  • Returned to install a new 6.5m galvanised power pole at the front boundary
  • Installed a green turret and jointed the cables in the pillar
  • Ran new 16mm XLPE from the turret up the pole and fitted pole top fuses to protect the underground consumer mains
  • Installed new 25mm aluminium overheads
Result

The home is back on a stable supply from a new galvanised pole. The underground consumer mains are now protected by pole top fuses.

Leaning Private Pole and Corroded Meter Box Replaced in Rose Bay
Rose Bay

Leaning Private Pole and Corroded Meter Box Replaced in Rose Bay

The private pole at a Rose Bay home was leaning and corroded at the base, and the meter box had corroded too. Replacing a pole and reconnecting the overhead service mains is Level 2 ASP work.

View case study →
Leaning Private Pole and Corroded Meter Box Replaced in Rose Bay
Rose Bay

Leaning Private Pole and Corroded Meter Box Replaced in Rose Bay

Why we were called

The private pole at a Rose Bay home was leaning and corroded at the base, and the meter box had corroded too. Replacing a pole and reconnecting the overhead service mains is Level 2 ASP work.

What we did
  • Isolated and disconnected the overhead service at the pole, then tested the meter panel to confirm it was de-energised
  • Removed the leaning, corroded pole and installed a new 6.5m galvanised steel private pole
  • Re-attached the overhead service mains with HSC connectors and re-terminated the consumer mains
  • Replaced the corroded meter box with a new 600x600mm galvanised steel box and an 80A service protection device
  • Tested, commissioned and sealed the installation, then restored supply
Result

The home is back on supply from a new, straight galvanised pole and a new steel meter box. Everything was tested and sealed before the power came back on.

Collapsed Timber Pole Replaced After Hours in Chatswood
Chatswood

Collapsed Timber Pole Replaced After Hours in Chatswood

Strong winds brought down the power line at a Chatswood home, leaving the timber pole leaning over the footpath and resting on a tree. The network made it safe, but a Level 2 ASP was needed to repair the damage.

View case study →
Collapsed Timber Pole Replaced After Hours in Chatswood
Chatswood

Collapsed Timber Pole Replaced After Hours in Chatswood

Why we were called

Strong winds brought down the power line at a Chatswood home, leaving the timber pole leaning over the footpath and resting on a tree. The network made it safe, but a Level 2 ASP was needed to repair the damage.

What we did
  • Responded after hours and disconnected the property from the network
  • Removed the collapsed hardwood pole, weakened by fungal growth and termites, along with the old 6mm copper aerial mains
  • Installed a new galvanised steel pole in the same spot, with the existing single phase consumer mains run inside it
  • Connected new 25mm aluminium overheads to the network and safely reconnected the home
  • Cleaned up the site once the new pole was in
Result

The home is back on a safe supply from a new galvanised pole. Damage to the mailbox, water meter and gate from the falling pole was noted for repair.

Emergency Pole Replacement After a Vehicle Impact in Enfield
Enfield

Emergency Pole Replacement After a Vehicle Impact in Enfield

A vehicle struck the private power pole at an Enfield property and the supply needed to be made safe and restored urgently.

View case study →
Emergency Pole Replacement After a Vehicle Impact in Enfield
Enfield

Emergency Pole Replacement After a Vehicle Impact in Enfield

Why we were called

A vehicle struck the private power pole at an Enfield property and the supply needed to be made safe and restored urgently.

What we did
  • Supplied a generator to keep the property powered
  • Removed the damaged pole and footing
  • Installed a new pole
  • Ran a three-phase overhead service to the Ausgrid asset pole
  • Tested and commissioned the new supply
Result

The damaged pole was replaced with a new pole and a three-phase overhead service, tested and commissioned.

Termite-Damaged Timber Pole Replaced With Galvanised Steel in Dulwich Hill
Dulwich Hill

Termite-Damaged Timber Pole Replaced With Galvanised Steel in Dulwich Hill

The existing timber pole at a Dulwich Hill property had been damaged by termites and was no longer safe to carry the service.

View case study →
Termite-Damaged Timber Pole Replaced With Galvanised Steel in Dulwich Hill
Dulwich Hill

Termite-Damaged Timber Pole Replaced With Galvanised Steel in Dulwich Hill

Why we were called

The existing timber pole at a Dulwich Hill property had been damaged by termites and was no longer safe to carry the service.

What we did
  • Installed a new 6.5m galvanised steel pole
  • Installed 16mm XLPE underground consumer mains
  • Tested the installation before energisation
Result

The property now has a galvanised steel pole that will not rot or attract termites.

Permanent Poles for a Two Dwelling Site in North Nowra
North Nowra

Permanent Poles for a Two Dwelling Site in North Nowra

A North Nowra site with two dwellings needed its temporary builders supply pole replaced with a full-length pole, plus a second private pole for the second dwelling.

View case study →
Permanent Poles for a Two Dwelling Site in North Nowra
North Nowra

Permanent Poles for a Two Dwelling Site in North Nowra

Why we were called

A North Nowra site with two dwellings needed its temporary builders supply pole replaced with a full-length pole, plus a second private pole for the second dwelling.

What we did
  • Removed the temporary builders supply pole and installed a full-length pole in the same spot
  • Installed a second private pole for the second dwelling
  • Brought the service mains up both poles and ran a new overhead to the second pole
  • Moved the smart meter from the builders supply board to the new switchboard on unit 1
  • Sealed and made ready both units' switchboards
Result

Both dwellings now have permanent private poles and switchboards ready for service, with the site off its temporary builders supply.

Temporary Builders Supply Pole for a Duplex in West Ryde
West Ryde

Temporary Builders Supply Pole for a Duplex in West Ryde

A West Ryde duplex site needed its existing supply disconnected and temporary builders power set up on a private pole that will later become permanent.

View case study →
Temporary Builders Supply Pole for a Duplex in West Ryde
West Ryde

Temporary Builders Supply Pole for a Duplex in West Ryde

Why we were called

A West Ryde duplex site needed its existing supply disconnected and temporary builders power set up on a private pole that will later become permanent.

What we did
  • Disconnected the existing supply
  • Installed a private pole on site
  • Set up a temporary builders supply on the pole
  • Installed 4G site cameras
Result

The site has construction power from the start, on a pole positioned to become the permanent supply for the duplex later.

Second Private Pole for a Duplex in Georges Hall
Georges Hall

Second Private Pole for a Duplex in Georges Hall

A Georges Hall duplex already had a private pole on one side and needed a second for the other dwelling.

View case study →
Second Private Pole for a Duplex in Georges Hall
Georges Hall

Second Private Pole for a Duplex in Georges Hall

Why we were called

A Georges Hall duplex already had a private pole on one side and needed a second for the other dwelling.

What we did
  • Installed a private pole for the second side of the duplex
  • Ran a new overhead to the pole
  • Relocated the meter from the temporary board to the permanent board
  • Completed the connection
Result

Both sides of the duplex now have their own private pole, with the second side moved off temporary supply onto its permanent board.

Two New Poles Installed in Wentworthville
Wentworthville

Two New Poles Installed in Wentworthville

A Wentworthville site needed two new poles set in place for its supply.

View case study →
Two New Poles Installed in Wentworthville
Wentworthville

Two New Poles Installed in Wentworthville

Why we were called

A Wentworthville site needed two new poles set in place for its supply.

What we did
  • Supplied and delivered two new poles to site
  • Set both poles in concrete
  • Fitted a J hook to each pole
  • Fitted a cap to each pole
Result

Both poles are set in concrete with hooks and caps fitted, ready for their overhead connections.

Private Pole and Three Phase Upgrade in Leichhardt
Leichhardt

Private Pole and Three Phase Upgrade in Leichhardt

A Leichhardt property was moving to a three-phase supply with a new private pole and a pole-mounted main switchboard.

View case study →
Private Pole and Three Phase Upgrade in Leichhardt
Leichhardt

Private Pole and Three Phase Upgrade in Leichhardt

Why we were called

A Leichhardt property was moving to a three-phase supply with a new private pole and a pole-mounted main switchboard.

What we did
  • Installed a new private power pole with earthing at the pole
  • Ran new three-phase overhead service mains and overhead consumer mains
  • Installed a new point of attachment hook centred on the roof
  • Mounted a 600x600 switchboard on the pole with three service fuses, a neutral link, a three-phase main switch and a circuit breaker
  • Ran three-phase consumer mains down the pole to the switchboard and connected them at the new point of attachment
Result

The property is now on a three-phase supply through its own private pole, with a new pole-mounted main switchboard and earthing in place.

Temporary Builders Supply and Private Pole in Rose Bay
Rose Bay

Temporary Builders Supply and Private Pole in Rose Bay

A Rose Bay building site needed its existing supply disconnected and a temporary builders supply set up on a private pole for construction.

View case study →
Temporary Builders Supply and Private Pole in Rose Bay
Rose Bay

Temporary Builders Supply and Private Pole in Rose Bay

Why we were called

A Rose Bay building site needed its existing supply disconnected and a temporary builders supply set up on a private pole for construction.

What we did
  • Disconnected the existing supply
  • Installed a new private pole
  • Installed a temporary builders supply on the pole
  • Installed a construction site camera
Result

The site now has temporary construction power on its own private pole, with a site camera in place.

Pole Replacement for Three Phase Supply in Earlwood
Earlwood

Pole Replacement for Three Phase Supply in Earlwood

An Earlwood property's existing pole needed replacing as part of a move to three-phase supply, with family members at home throughout the works.

View case study →
Pole Replacement for Three Phase Supply in Earlwood
Earlwood

Pole Replacement for Three Phase Supply in Earlwood

Why we were called

An Earlwood property's existing pole needed replacing as part of a move to three-phase supply, with family members at home throughout the works.

What we did
  • Disconnected the mains at the point of attachment
  • Removed the existing pole
  • Installed a new 7.2m pole for the three-phase supply
  • Supplied a complimentary generator to keep the household powered during the works
Result

The property now has a new 7.2m pole ready for its three-phase supply, and the household kept power to its appliances throughout the works.

Private Pole Install and Overhead Connection in North St Marys
North St Marys

Private Pole Install and Overhead Connection in North St Marys

A North St Marys property needed a private pole installed and connected to the overhead supply, ready for three-phase metering.

View case study →
Private Pole Install and Overhead Connection in North St Marys
North St Marys

Private Pole Install and Overhead Connection in North St Marys

Why we were called

A North St Marys property needed a private pole installed and connected to the overhead supply, ready for three-phase metering.

What we did
  • Installed a new private pole
  • Made the overhead connection to the pole
  • Fitted the three-phase meter sticker and tagged the installation
  • Lodged the meter application
Result

The private pole is installed and connected, with the site tagged and the three-phase meter application lodged.

Private Pole and Three Phase Switchboard in North Sydney
North Sydney

Private Pole and Three Phase Switchboard in North Sydney

A North Sydney property needed a new private pole and a new three-phase main switchboard.

View case study →
Private Pole and Three Phase Switchboard in North Sydney
North Sydney

Private Pole and Three Phase Switchboard in North Sydney

Why we were called

A North Sydney property needed a new private pole and a new three-phase main switchboard.

What we did
  • Dug the footing and concreted in a new private pole
  • Installed a new 600x600 three-phase switchboard with a pre-made panel
  • Fitted three-phase surge protection and a new earth stake
  • Installed a fascia bracket and ran the overhead cable and 16mm XLPE mains
Result

The property now has its own private pole and a new three-phase switchboard with surge protection and earthing in place.

Private Pole Install and Permanent Connection in Georges Hall
Georges Hall

Private Pole Install and Permanent Connection in Georges Hall

A Georges Hall property needed a new private pole and a permanent single-phase connection, with provision left for an underground supply later.

View case study →
Private Pole Install and Permanent Connection in Georges Hall
Georges Hall

Private Pole Install and Permanent Connection in Georges Hall

Why we were called

A Georges Hall property needed a new private pole and a permanent single-phase connection, with provision left for an underground supply later.

What we did
  • Installed a new private pole
  • Left provision in the pole for a future underground supply
  • Ran new single-phase overhead service mains to the pole
  • Completed the metering and permanent connection
Result

The property now has a permanent single-phase supply on its own private pole, with provision in place for an underground connection later.

New Private Pole and Overhead Service in Killara
Killara

New Private Pole and Overhead Service in Killara

A Killara property needed a new private pole with a single-phase overhead service from the network pole.

View case study →
New Private Pole and Overhead Service in Killara
Killara

New Private Pole and Overhead Service in Killara

Why we were called

A Killara property needed a new private pole with a single-phase overhead service from the network pole.

What we did
  • Installed a new private pole
  • Supplied and installed a private pillar
  • Ran single-phase overhead service mains from the network pole to the private pole
  • Fitted fuses to protect the existing underground consumer mains
Result

The property is now fed from the network through its own private pole, and the existing underground consumer mains are protected by new fuses.

Request your free power pole quote

Fill out the form and our expert team will get back to you shortly. Whether it’s an emergency or a planned installation, we’re ready to help: fast, safe, and professional.